Project Name Location Tonnage *Plant Capacity Year
Modularized Gas Turbine Enclosure Design U.S.A. - - Ongoing
Tambak Lorok 9HA ST Piping Indonesia 18 1,338 MW Ongoing
Tambak Lorok 9HA GT Piping Indonesia 11 1,338 MW Ongoing
Oumache Djezair (Algeria) 4 units 9FA Piping + Loose Hardware Algeria 132 1,338 MW Ongoing
El Bracho Combined Cycle L41/L42 Argentina 308 468 MW Ongoing
Zeran Coal Fired PP - HRSG Piping Poland 226 490 MW Ongoing
NCPF Lot Cheminee Soc Lot 14501 France 41 - Ongoing
Non Critical Boilers and Condensers France 43 - Ongoing
Muara Tawar Add On Turbine Piping Indonesia 99 150 MW Ongoing
TOTAL   878 mt 5.122 MW  