Projects

LNG Projects

Sayfaİci-1_EGLNG Projesi, Spool Sevkiyati

LNG Projects

Cimtas Pipe has successfully delivered over 88,000 tons of prefabricated pipe spools to several LNG projects globally. Cimtas Pipe LNG program has been ongoing with multiple projects and Cimtas started providing and using its own “Cimtas fittings “for these projects starting Q1 2016.

Project Name Location Tonnage *Plant Capacity Year
Corpus Christi LNG Train 1-2 U.S.A. 14,250 4.5 2015
Angola LNG (Additional) Angola 1,300 5.2 2014-2015
Sabine Pass LNG Train 3-4 U.S.A. 13,700 9 2014-2015
Sabine Pass LNG Train 1-2 U.S.A. 14,250 9 2013-2014
AP LNG Australia 6,900 4.5 2012-2013
Gladstone LNG Australia 12,500 7 2012-2013
Queensland LNG Australia 10,100 8.5 2012-2013
Angola LNG Angola 7,250 5.2 2009-2010
EGLNG Equatorial Guinea 2,500 3.4 2005-2006
ELNG Egypt 5,350 7.2 2003-2004
TOTAL   88,100 63.5  
*Total of 16 trains with 63.5 million tons per annum capacity